ALMM List-II and DCR rules for solar EPCs: what changed after 1 June 2026
ALMM List-II is MNRE's approved list of solar PV cells, and since 1 June 2026 it decides which modules a net-metering or open-access project may use. Right now most rooftop and open-access projects commissioned on or before 31 December 2026 are exempt from the cell list but still need List-I modules; subsidised PM Surya Ghar homes still need DCR modules; and "Give It Up" homes have until 31 March 2027. This guide sets out the rule for each project type, the memo behind it, and the records an EPC should keep for every installation.
We reply within 1 business hour · No obligation
Also Zoho Creator Registered, Zoho Catalyst, AWS and Shopify Partner
What an EPC needs to take away
- List-I covers modules, List-II covers the cells inside them. A project under ALMM needs List-I modules built with List-II cells.
- The cell exemption to 31 December 2026 is about the commissioning date, not the order date, so the date on your commissioning report matters most.
- DCR is a separate test set by each MNRE scheme. ALMM relief never relaxes it.
- Private behind-the-meter captive plants sit outside both ALMM lists; Government and PSU behind-the-meter plants do not.
- Proof lives at installation level: which modules, which serials, which cell list entry, which date, which metering type.
What are ALMM List-I and List-II, and how do they differ?
ALMM stands for the Approved List of Models and Manufacturers, kept by the Ministry of New and Renewable Energy. List-I names approved solar PV modules. List-II names approved solar PV cells, and was first issued on 31 July 2025. Where a project falls under ALMM, it must use modules from List-I that are in turn made with cells from List-II.
For years, only the module list mattered on most rooftop jobs. A module could be assembled in India from imported cells and still appear on List-I. List-II closes that gap by asking where the cell itself was made, which is why the change shows up in module prices, lead times and the paperwork a buyer must collect.
Where DCR fits in
DCR means Domestic Content Requirement. It is a condition written into specific MNRE schemes, not into ALMM. Under PM Surya Ghar: Muft Bijli Yojana, the subsidy (Central Financial Assistance, CFA) is paid only when the modules are domestically made from domestically made cells; a single non-DCR module makes the whole installation ineligible for CFA. MNRE's 4 August 2026 clarification states plainly that ALMM orders do not relax any DCR rule, and that DCR follows each scheme's own guidelines.
ALMM List-I and List-II
- A list of approved module and cell makers and models
- Applies by project category (net metering, open access, Government)
- Has dated exemption windows
- Revised often: List-II was on its 14th revision dated 6 November 2026 when we checked
DCR
- A condition inside a scheme, such as PM Surya Ghar CFA
- Asks for domestic modules made from domestic cells
- Has no ALMM exemption window
- Missing it costs the customer the subsidy, not only a compliance note
What changed between December 2024 and November 2026?
The cell rule was announced in December 2024 for projects commissioned from 1 June 2026, held firm in May 2026, then softened in July 2026 with a commissioning window to 31 December 2026 for net-metering and open-access projects.
- The original orderNet-metering and open-access projects commissioned on or after 1 June 2026 must use List-I modules and List-II cells.
- List-II publishedThe first approved list of solar PV cells appears. Revisions follow through 2026.
- No blanket extensionMNRE refuses a general delay and offers case-by-case relief for projects with modules already installed, claimed on a NISE portal by 30 June 2026.
- Give It Up reliefResidential net-metering consumers who forgo the PM Surya Ghar subsidy and apply through the National Portal are exempted from List-II till 31 March 2027.
- Government buildingsA separate clarification for rooftop solar on Government buildings, using bid-date cut-offs and, for projects without a bid, the commissioning date.
- The window to 31 DecNet-metering and open-access projects may commission with exemption from List-II cells until 31 December 2026. This memo supersedes the May and June memos.
- The fine printCells only, List-I still needed, no NISE application, Give It Up stays to 31 March 2027, metering types defined, behind-the-meter rules set, DCR untouched.
Dates and memo numbers as read on mnre.gov.in and pib.gov.in on 22 November 2026. Rules change; check the official portal before you plan a commissioning date.
Which rule applies to which kind of solar project?
It depends on two facts you can check on any job file: how the plant connects to the grid (net metering, open access or behind the meter) and whether the customer is claiming a scheme subsidy. The commissioning date then decides whether the cell exemption still helps.
| Project type | List-I modules | List-II cells | DCR |
|---|---|---|---|
| Home rooftop under PM Surya Ghar, claiming CFA | Yes | Covered by DCR | Mandatory domestic modules from domestic cells |
| Home rooftop, PM Surya Ghar "Give It Up" via the National Portal | Yes | Exempt till 31 Mar 2027 | Not a CFA case |
| Other net metering: C&I or home rooftops outside the scheme, gross metering, net billing, net feed-in, virtual or group net metering | Yes | Exempt if commissioned by 31 Dec 2026, required after | Only if a scheme you claim asks for it |
| Open-access projects | Yes | Exempt if commissioned by 31 Dec 2026, required after | Only if a scheme you claim asks for it |
| Behind-the-meter captive plant of a private consumer | Outside ALMM | Outside ALMM | Only if a scheme you claim asks for it |
| Behind-the-meter plant of a Government body or PSU | Yes | Required after 31 Dec 2026 | As per the scheme or tender |
| Rooftop on Government buildings | Read the 6 July 2026 clarification: cut-offs depend on the bid date, or on the commissioning date where there was no bid. | ||
A summary of MNRE memos, not legal advice. Your DISCOM, the scheme portal and your compliance lead decide each case. Rules change; check the official portal.
Three illustrative cases that trip EPC teams up
- The mixed roof. A home owner first asks for the subsidy, then switches to Give It Up after seeing the DCR module price. The job file must show the switch on the portal before any non-DCR module leaves the warehouse.
- The late commissioning. A C&I net-metering plant ordered in October with non-List-II cells, then delayed by a roof repair into January 2027. After 31 December 2026 the exemption no longer covers it.
- The captive plant that becomes net metered. A behind-the-meter factory plant is outside ALMM, but if the owner later applies for net metering, the plant moves into a category with ALMM rules. Decide the metering route before you buy modules.
Project rule checker
Which ALMM and DCR rule applies to your next project?
Pick the project type and the planned commissioning date. The checker reads the memos summarised above and lists what the modules and cells must be, plus the records to collect.
Based on MNRE memos read on 22 November 2026. A starting point for your team, not a ruling. Rules change; check the official portal.
What records should an EPC keep for every installation?
Keep enough to prove, months later, which modules went onto which roof, what list they were on that day, and when the plant was commissioned. If a DISCOM, a scheme officer or a customer asks, you should answer from one job record rather than from a supplier's inbox.
Most of the trouble we see in solar operations is not a wrong module. It is a right module with no proof: a DCR document saved on a site engineer's phone, a serial list typed into a spreadsheet after dispatch, or a commissioning date that differs between the DISCOM portal and the invoice. Here is the record set we suggest per installation.
- Project categoryMetering route (net metering, gross, net billing, VNM, GNM, open access or behind the meter) and the scheme claimed, if any. Set this before the purchase order, because it decides the module type.
- Scheme optionFor PM Surya Ghar homes, the portal application ID and whether the customer chose CFA or Give It Up, with the date the option was recorded.
- Module model and List-I entryThe exact model, the maker and the List-I entry your team checked, with the date of the list version.
- Cell source and List-II entryThe cell maker named by the module supplier and the List-II revision checked. Needed for anything commissioning after the exemption ends, and for every DCR job.
- Supplier papersThe supplier's domestic content documents for DCR stock, attached to the purchase invoice they belong to, not to the project folder in general.
- Serial numbersEvery module serial scanned at goods receipt, at dispatch to site and at installation, so one serial links the invoice, the site and the warranty.
- DatesPlanned commissioning, actual commissioning, DISCOM inspection and net-meter installation, each with its evidence file.
- Decision logWho decided the category, which memo they relied on and when. If a rule changes mid-project, this is what your compliance lead will ask for first.
The PM Surya Ghar vendor software page covers the full scheme workflow per customer, from portal application to subsidy release, and it is the page to read if subsidised homes are most of your work.
What do distributors and module makers need to change?
Stock now has to carry its rule with it. A pallet of modules is no longer just a model and a wattage: it is DCR or non-DCR, List-II cells or not, and the warehouse must know before it ships to a project.
Distributors and dealers
- Tag each item and batch as DCR or non-DCR, with the cell source
- Hold non-DCR stock back from orders linked to a CFA project
- Flag non-List-II stock that would reach a site after 31 December 2026
- Keep supplier papers per batch so they can travel with each invoice
Module manufacturers
- Trace cell lots to finished module serials in production records
- Keep List-I and List-II entries against each model and cell source
- Issue domestic content papers per invoice, not per month
- Watch each List-II revision for changes to your cell suppliers
EPC and installer teams
- Lock the project category at quotation, not at dispatch
- Plan commissioning dates with a buffer before 31 December 2026
- Scan serials at site, not at the office a week later
- Keep a decision log for every project caught between two rules
For the distribution side, our page on CRM for solar distributors shows how orders, dealers and stock connect. Manufacturers will find cell-to-module traceability covered in our guide to solar manufacturing software on Zoho.
How can Zoho track ALMM and DCR records per project?
Zoho keeps the records; it does not decide the rule. The project record holds the category and dates, Zoho Inventory holds serials and stock tags, and a small Zoho Creator app can block a dispatch that breaks the rule your team has set.
| Record or check | Zoho app | Type | Notes |
|---|---|---|---|
| Module serial numbers at receipt, dispatch and site | Zoho Inventory | Native | Serial tracking is a standard item setting; scanning at site uses the mobile app |
| DCR or non-DCR tag, cell maker, List-I and List-II entry per item | Zoho Inventory | Configuration | Custom fields on items, kept up to date after each list revision |
| Project category, scheme option and commissioning dates | Zoho CRM, or Projects for job plans | Configuration | Fields, layouts and a workflow alert as 31 December 2026 gets close |
| Supplier papers attached to the right invoice | Zoho Inventory with Zoho WorkDrive | Configuration | One folder per purchase invoice, linked from the bill |
| Block non-DCR stock from a CFA project's sales order | Deluge, or a Creator app | Custom | A rule your team approves in writing, tested before go-live |
| Dashboard of projects at risk of missing the cell window | Zoho Analytics | Configuration | Planned commissioning date against category and stock type |
| PM Surya Ghar, NISE or DISCOM portal entries | Manual, reference saved in Zoho | Outside Zoho | Your team works on the government portal and records the reference ID on the job |
Most EPCs start with the project record and serial tracking, because those two answer the question a scheme officer asks most: which modules are on this roof? The dispatch block comes later, once the team trusts the tags. If you run projects end to end, our solar EPC software page shows the full job record from survey to handover, and DISCOM approval tracking covers the inspection and net-meter stages in detail.
How we can help
Three ways to put ALMM and DCR records on Zoho
We have delivered many solar projects, and after looking at how your team buys, stores and installs modules, we recommend the option that fits your business.
Option 1Zoho Solar, for ALMM and DCR records
Solar workflows configured on Zoho apps: project categories, serial tracking, supplier papers and date alerts, with no custom code.
Option 2Zoho Solar + Custom, for ALMM and DCR records
Zoho apps plus custom-built apps, portals and integrations, for example a dispatch check that stops non-DCR stock reaching a subsidised home.
Option 3Complete end-to-end solar product, for ALMM and DCR records
Our complete solar business product covering the whole value chain, for firms that make, distribute and install, and want one system for all of it.
Not sure which records you are missing today?Bring one recent job file; we will trace it from purchase order to commissioning with you.
Book your meeting with our solar expert todayWhat clients say
Reviews from our published Zoho clients
These quotes come from clients in other industries who have allowed us to publish them. Every example on this page is illustrative.
The team at Elite Tech Corporation is highly knowledgeable and extremely supportive. They took the time to understand each of our business use cases in detail and approached every requirement with a strong implementation mindset.
What stood out most was their structured approach, clarity in communication, and commitment to aligning technology with practical, on-ground operations rather than offering generic solutions.
Your understanding of our requirements and customization of Zoho Books have positively impacted our operations. The successful implementation of APIs and workflows has streamlined processes.
Which official documents should you read yourself?
Read the memos, not summaries of them, including this one. Each is published on the Ministry of New and Renewable Energy website (mnre.gov.in), under its notices and ALMM sections. We read every item below on 22 November 2026.
- MNRE office memorandum No. 283/53/2026 dated 18 July 2026: the List-II window to 31 December 2026 for net-metering and open-access projects
- MNRE office memorandum No. 283/54/2026 dated 4 August 2026: clarifications on scope, metering types, behind-the-meter plants and DCR
- MNRE office memorandum No. 318/84/2024 dated 8 June 2026: List-II exemption for PM Surya Ghar Give It Up cases
- MNRE office memorandum No. 283/34/2026 dated 6 July 2026: rooftop solar on Government buildings
- PM Surya Ghar: Muft Bijli Yojana operational guidelines on MNRE's site: DCR condition for CFA and vendor registration
- ALMM List-I and List-II with their revisions: the current list, not an old download, before each purchase
As a Zoho Advanced Partner, Elite Tech Corp builds the systems that hold these records. We are not a scheme agency, we hold no MNRE or DISCOM approval, and we do not give legal rulings. Your compliance lead or consultant decides how a rule applies to a project.
FAQ
Questions EPCs ask about ALMM List-II and DCR
Have a project caught between two rules? Send us the job details and a solar consultant will reply within 1 business hour.
Book your meeting with our solar expert todayWhat is the difference between ALMM List-I and ALMM List-II?
List-I is MNRE's approved list of solar PV modules and List-II is its approved list of solar PV cells. A project that falls under ALMM must use List-I modules made with List-II cells. List-II was first issued on 31 July 2025 and is revised often, so check the current version before each purchase.
Do rooftop net-metering projects need List-II cells in 2026?
Not if they are commissioned on or before 31 December 2026. MNRE's memo of 18 July 2026 lets net-metering and open-access projects commission with exemption from List-II cells until that date, and the 4 August 2026 clarification says no application on the NISE portal is needed. List-I modules are still required, and projects commissioned after 31 December 2026 must use List-II cells. Rules change; check the official portal.
Can a PM Surya Ghar home use non-DCR modules?
Only if the customer gives up the subsidy. For a home claiming Central Financial Assistance, every module must be domestically made from domestically made cells, and one non-DCR module makes the installation ineligible. Residential net-metering customers who choose the Give It Up option and apply through the PM Surya Ghar National Portal are exempt from List-II until 31 March 2027, though List-I modules are still needed.
Does the 31 December 2026 exemption relax DCR rules?
No. MNRE's 4 August 2026 clarification states that ALMM orders do not relax any DCR condition in its schemes. DCR follows each scheme's own guidelines, so a subsidised PM Surya Ghar system still needs DCR modules whatever the commissioning date.
Are behind-the-meter solar plants covered by ALMM?
Behind-the-meter captive plants of private consumers are outside ALMM List-I and List-II, according to the 4 August 2026 clarification. Behind-the-meter plants of Government bodies and PSUs need List-I modules, and List-II cells if commissioned after 31 December 2026. If a private plant later applies for net metering, it moves into a category where ALMM applies.
Which metering types count as net metering for the ALMM exemption?
The 4 August 2026 clarification includes gross metering, net billing, net feed-in, virtual net metering and group net metering, as well as plain net metering. Behind-the-meter setups are not included.
What should an EPC record to prove a project followed the rules?
Keep the project category and metering route, the scheme option chosen, the module model with its List-I entry, the cell source with the List-II revision checked, supplier domestic content papers per invoice, every module serial from receipt to installation, and the commissioning and inspection dates with evidence. A short decision log showing which memo your team relied on helps if a rule changes mid-project.
Can Zoho stop non-DCR stock from going to a subsidised project?
Zoho Inventory tracks serial numbers as a standard feature and can carry DCR, cell source and list fields on each item through configuration. Blocking a sales order or dispatch that mixes non-DCR stock with a CFA project needs a custom rule in Zoho Creator or Deluge, which we build and test with your team before it goes live.