Solar EPC project cost calculation: how EPC companies build a cost sheet and set a price they can defend
Solar EPC project cost calculation starts with a bill of materials priced at today's supplier rates, then adds installation labour, transport, approvals and testing to get the direct cost. On top of that, an EPC firm adds a share of its overheads and a contingency for site surprises, and only then sets the selling price from a target margin. The figure per watt or per kilowatt comes last, as a check, not as the starting point. This guide shows each layer, a sample cost sheet and a calculator you can fill with your own rates.
We reply within 1 business hour · No obligation
The short version
- Cost first, price second. A per-kW price copied from the market hides what your own project will really cost.
- The bill of materials is the biggest block, but the leaks usually sit in labour days, cable lengths, structure changes and approval delays.
- Overheads and contingency belong in every estimate as separate lines, so you can see them shrink when a deal is squeezed.
- Set the price from a target margin on the selling price. Adding the same percentage as markup on cost earns you less than you think.
- Keep the estimate on the project record and compare it with actual purchase and site cost every week, not after handover.
What does a solar EPC project cost include?
A solar EPC project cost includes everything the firm spends to hand over a working plant: material, the people and equipment that install it, the approvals and testing that make it legal to run, and a fair share of the cost of running the company. Margin sits on top of that cost and is not part of it.
Estimators who skip a layer usually do it by accident. The material list is checked twice, but nobody prices the second visit after the inspection, the crane for the inverter, or the weeks the project manager spends chasing a net-meter. The table below is a list we use when reviewing an EPC firm's costing template.
| Layer | What sits in it | How it is usually measured | What often gets missed |
|---|---|---|---|
| Modules | Panels of the chosen make, wattage and technology | Rate per watt-peak times the DC capacity | Spare modules, breakage in transit, the approved-list rule for scheme or net-metering work |
| Inverter and storage | String or central inverter, optimisers, batteries where quoted | Per unit, sized to the AC capacity | Monitoring dongle or data logger, extended warranty, a spare for large plants |
| Mounting structure | Rails, purlins, columns, clamps, fasteners, ballast or anchors | Per kWp from the structure drawing, or by weight | Galvanising grade, extra height for shade or walkways, roof waterproofing at each anchor |
| Electrical balance of system | DC and AC cable, connectors, combiner boxes, protection devices, earthing, lightning arrester, metering panel | Metres of cable from the layout; per unit for boxes and devices | Cable route changes after survey, cable trays, conduit, the earthing pit count |
| Labour | Installers, electricians, supervisor, engineer at commissioning | Crew-days times the day rate, plus food and stay for outstation work | Idle days waiting for material or a shutdown window, the snag-list visit |
| Site logistics | Freight, unloading, lifting, scaffolding, safety gear | Per trip or lump sum per project | Crane hire for tall roofs, storage on site, security for material left overnight |
| Approvals and testing | Application fees, liaison visits, inspection, meter testing, documentation | Lump sum per project type | Repeat visits when the inspector raises a point, the staff time spent chasing approval |
| Overheads | Office, design team, sales cost, vehicles, software, insurance | A percentage of direct cost, worked out from last year's books | Using a percentage nobody has checked since the firm was smaller |
| Contingency | Allowance for unknowns on that site | A percentage of direct cost, higher for old roofs and remote sites | Dropping it to win the order, then losing it on the first change |
| Service reserve | Free visits promised during the workmanship warranty, cleaning if included | Visits times the cost of a visit | Promises made in the proposal that never reach the cost sheet |
Make and model choices change every row. Price from your own supplier quotes, dated, for the week you send the proposal.
From survey to price
How do you calculate solar EPC project cost step by step?
Work from the site survey to a priced bill of materials, add execution and approval cost to reach direct cost, add overheads and contingency to reach full cost, and then divide full cost by one minus your target margin to get the selling price before tax.
- Lock the survey data.Roof or land dimensions, shade, structure type, cable route, distance to the meter, sanctioned load and the customer's bills. A cost built on a guessed cable route is a guess.
- Fix the capacity and the denominator.Write down the DC capacity in kWp and the AC capacity of the inverter. Every per-watt figure later must say which one it divides by.
- Build the bill of materials from the design.Quantities come from the layout, not from a template copied off the last project. Price each line at a dated supplier rate.
- Price execution.Crew-days by stage (structure, modules, wiring, testing), transport trips, lifting, and outstation costs where the site is far from your base.
- Add approvals, testing and documentation.Fees, liaison time, inspection visits and the handover file. Treat this as a cost line, not a favour your project manager does for free.
- Add overheads and contingency.Use an overhead rate worked out from your own books, and a contingency that reflects the risk on this site.
- Set the price on margin, then sense-check per watt.Price equals full cost divided by (1 minus target margin). Then divide by the DC watts and compare with your recent wins and losses, not with a number from a forum.
What does a sample 50 kWp rooftop cost sheet look like?
Here is the method applied to a sample 50 kWp factory rooftop. Every rate below is a sample chosen to show the arithmetic. None of them is a market price, and none should be used to quote a customer.
| Line (Sample) | Basis | Amount (₹, Sample) |
|---|---|---|
| Modules | 50,000 Wp at ₹22 per Wp | 11,00,000 |
| Inverter | 50 kWp at ₹3,000 per kWp | 1,50,000 |
| Mounting structure | 50 kWp at ₹4,000 per kWp | 2,00,000 |
| Cables, protection, earthing | 50 kWp at ₹3,000 per kWp | 1,50,000 |
| Installation labour | 40 crew-days at ₹1,500 | 60,000 |
| Transport and lifting | Lump sum | 40,000 |
| Approvals, liaison and testing | Lump sum | 30,000 |
| Direct cost | Sum of the lines above | 17,30,000 |
| Overheads | 8% of direct cost | 1,38,400 |
| Contingency | 3% of direct cost | 51,900 |
| Full cost | Direct cost plus overheads and contingency | 19,20,300 |
| Selling price before GST | Full cost ÷ (1 − 0.12) for a 12% margin | 21,82,159 |
| Margin earned | Price minus full cost | 2,61,859 |
| Price per watt (DC) | Price ÷ 50,000 Wp | about 43.64 |
Two things stand out even in a made-up example. First, the module line is large, so a small change in the module rate between quote and purchase order moves the margin more than any other line. Second, overheads and contingency together are bigger than the margin. If a salesperson gives away the contingency to close the deal, the firm is already eating into its profit before the crew reaches site.
Free cost sheet calculator
Can you calculate your own solar project cost here?
Yes. Replace the sample rates with your own supplier and crew rates and the sheet works out direct cost, full cost, the price at your target margin and the price per watt. It runs in your browser and sends nothing unless you choose to share it with us.
Estimate only · before GST
- Material
- ₹0
- Execution and approvals
- ₹0
- Direct cost
- ₹0
- Overheads and contingency
- ₹0
- Full cost
- ₹0
- Selling price at your margin
- ₹0
- Margin earned
- ₹0
- Price per watt (DC)
- ₹0
Estimate only. Sample defaults are not market prices. GST, subsidy and financing are left out on purpose; see the sections below.
Should a solar EPC firm price on margin or on markup?
Price on margin. Margin is profit as a share of the selling price, which is how your books and your bank will read the project. Markup is profit as a share of cost, and it always gives a smaller margin than the same percentage suggests.
Take the sample full cost of ₹19,20,300. Add a 12% markup and the price becomes ₹21,50,736, which leaves ₹2,30,436 of profit. That is only about 10.7% of the price. Divide by 0.88 instead and the price is ₹21,82,159, which leaves the full 12%. On one project the gap is about ₹31,000; across a year of projects it is the difference between the plan and the result.
The confusion usually starts when the owner thinks in margin and the estimator's template quietly uses markup. Write the formula at the top of the template, name the cell "target margin on price", and the argument goes away.
What margin should you aim for?
No single figure suits every firm, so this guide does not offer one. Work it backwards: take the profit the business needs this year, add the overheads that the overhead rate does not already cover, and divide by the sales you can realistically win. Then compare with your recent orders. If the margin you need is far above what you actually won at, the issue is cost or segment, not the formula.
Why does cost per watt differ between solar projects?
Cost per watt differs because some costs grow with capacity and others stay almost the same whatever the size. Modules and structure scale with kilowatts; survey, design, approvals, transport and the commissioning visit do not. Spread a fixed cost over 3 kWp and it hurts; spread it over 300 kWp and it nearly disappears.
Home rooftop
Fixed costs dominate
Survey visits, paperwork, a short crew day and scheme documentation are close to the same for a small system as for a slightly bigger one, so the per-watt figure is high. Watch the time spent per lead before the order.
Commercial and industrial roof
Structure and access drive it
Sheet roofs, RCC roofs and old roofs need different structures and anchoring. Shutdown windows, safety rules and lifting make labour less predictable, so contingency matters more here.
Ground-mounted plant
Civil and evacuation join the sheet
Land preparation, piling or foundations, fencing, internal roads and the line to the grid point become big lines of their own. Keep land and evacuation visible as separate lines rather than folding them into a per-watt number.
DC watts or AC watts?
Say which one you divide by, every time. A plant with more DC panels than inverter capacity looks cheaper per DC watt and more expensive per AC watt. When customers compare your quote with another firm's, a mismatch in the denominator can make an honest quote look expensive.
Where the estimate drifts
Why does solar project cost change after work begins?
Because the estimate was built on assumptions that the site, the supplier or the approval process later changes. The fix is not a bigger contingency on every job; it is catching each change on the day it happens and deciding whether the customer or the firm pays for it.
Survey gaps
A cable route measured on a phone photo, a parapet height not recorded, a roof that cannot take the load. Each one becomes extra material or a redesign.
Rate movement
The proposal used last month's module or cable rate and the purchase order goes out at this month's. Date every rate and give proposals a validity period.
Scope creep
A walkway, an extra earthing pit or a longer AC run requested on site and never priced. Write a change note before the work, not after.
Idle crew days
Material arrives late or the customer's shutdown moves. The crew still costs money, and it rarely appears on the original sheet.
Approval loops
Each repeat inspection visit, missing document or corrected drawing costs staff time and delays the final payment.
Module and cell rules
Scheme and net-metering projects have approved-list and domestic-content rules for modules and cells. Buying the wrong stock can mean replacing it. Check the current rule on the MNRE site before you order.
How should GST and subsidy appear in a solar EPC cost sheet?
Keep both out of the cost and margin calculation and show them separately on the quote. Build cost and price before tax, then apply the GST treatment your tax adviser confirms for your contract, because the way supply and installation are split in the contract can change it.
Input tax you can claim back is not a cost; tax you cannot claim back is. If your estimator adds tax into material rates for some suppliers and not others, the cost sheet stops being comparable from one project to the next. Record every supplier rate before tax and keep the tax rate as its own field.
A government subsidy on a home rooftop system is a benefit to the consumer under that scheme's rules. It does not change what the plant costs you to build. Show the price, the expected subsidy and the amount the customer pays as three separate lines, and do not promise a subsidy amount or a release date on the customer's behalf. Rules change; check the official portal at pmsuryaghar.gov.in for the residential scheme and the MNRE site for module rules before you quote.
GST registration and returns: gst.gov.in. This is a costing guide, not tax advice.
How do you track estimated cost against actual cost on each project?
Keep the approved estimate as a frozen baseline on the project, then post every purchase order, material issue, crew-day and expense against the same project code as it happens. A weekly look at estimate against actual, line by line, shows a leak while there is still time to recover it.
In many EPC firms, the estimate lives in one spreadsheet, purchases in the accounts software and site expenses in a chat group. Nobody sees the real margin until the project is closed, and by then the next ten quotes have been priced with the same wrong rates. The point of a system is to close that loop: actual costs from finished projects should update the rates used for the next estimate.
What Zoho does natively, what needs configuration and what needs custom work
| Costing job | Zoho apps and setup used | Type |
|---|---|---|
| Item master with dated purchase rates | Items and price lists in Zoho Inventory or Zoho Books, with vendor rates kept per item | Native |
| Quote raised from the solar deal | Quotes in Zoho CRM, or estimates in Zoho Books, raised from the deal record | Native |
| Standard kits per system size | Composite items or bundles in Zoho Inventory, set up for your common system sizes and structure types | Configuration |
| Costs posted against a project | Purchase bills, expenses and timesheets tagged to a project in Zoho Books, or reporting tags on each transaction | Configuration |
| Estimate against actual report | A Zoho Analytics dashboard joining the frozen estimate with posted cost per project and per line | Configuration |
| Costing engine with overhead, contingency and margin rules | A Zoho Creator app that builds the sheet from survey data, applies your formulas and pushes the quote to Zoho CRM | Custom build |
| Quantities from the design tool | Export from your layout or simulation tool into the costing app, by file import or an API where the tool offers one | Integration |
Which Zoho editions and add-ons you need depends on users and volume; we confirm that in the first meeting rather than guess here.
For the full project flow, from enquiry to commissioning, see our solar EPC software page. The quote and material pieces are covered in more depth on solar quotation software, solar BOM management and solar purchase management.
Tools for tracking cost
Which Zoho Projects and Books plans track EPC project cost?
Budgets, timesheets and project billing are plan features. Compare Projects and Books editions to see where cost tracking for an EPC job becomes possible.
| Feature | Free | Premium | Enterprise | Ultimate |
|---|---|---|---|---|
| Users and access | ||||
| Read-only users | – | – | 10 | 100 |
| Resources | – | – | Add-on | 100 |
| Client users | – | Add-on | Add-on | Add-on |
| Lite users | – | – | – | Add-on |
| Custom profiles and roles | – | – | ✓ | ✓ |
| User hierarchy | – | – | ✓ | ✓ |
| Projects and storage | ||||
| Number of projects | 3 | Unlimited | Unlimited | Unlimited |
| Storage | 5 GB | 100 GB | 120 GB | 15 GB per user, min 150 GB per org |
| Project templates | – | 20 | 30 | 50 |
| Sandbox | – | – | 1 | 10 |
| Tasks and Gantt | ||||
| Gantt charts | ✓ | ✓ | ✓ | ✓ |
| Task dependencies | Within project, finish-to-start only | Within project, all four types | Across projects, all four types | Across projects, all four types |
| Recurring tasks | – | ✓ | ✓ | ✓ |
| Critical path | – | – | ✓ | ✓ |
| Baselines | – | – | 15 per project | 15 per project |
| Task blueprints | – | 2 per layout | 25 per layout | 50 per layout |
| Timesheets and budgets | ||||
| Time logs and timesheets | – | ✓ | ✓ | ✓ |
| Timesheet approvals | – | ✓ | ✓ | ✓ |
| Multi-user, multi-project timesheets | – | – | – | ✓ |
| Project budgets | – | ✓ | ✓ | ✓ |
| Earned value management | – | ✓ | ✓ | ✓ |
| Business calendars | – | 1 | 3 | 20 |
| Reports and dashboards | ||||
| Workload report | – | Per project | Across projects | Across projects |
| Planned vs actual report | – | Per project | Across projects | Across projects |
| Custom reports per module | 1 preset report | 20 | 50 | 250 |
| Project dashboards | 1 | 5 | 10 | Unlimited |
| Global dashboards | 1 | 1 | 5 | Unlimited |
| Automation | ||||
| Workflow rules | 2 per layout | 2 per layout | 20 per layout | 40 per layout |
| Webhook calls | 20 per day | 200 per day | 2,000 per day | 10,000 per day |
| Custom function runs | 50 per day | 500 per day | 5,000 per day | 10,000 per day |
| Zoho Flow actionsMore via Flow credits | 100 per month | 100 per month | 100 per month | 100 per month |
| Integrations | ||||
| Zoho CRM | ✓ | ✓ | ✓ | ✓ |
| Zoho Books and Zoho Invoice | – | ✓ | ✓ | ✓ |
| Zoho Desk | – | – | ✓ | ✓ |
| Power BI | – | – | ✓ | ✓ |
| Slack and Microsoft Teams | ✓ | ✓ | ✓ | ✓ |
| GitHub, GitLab and Bitbucket | – | ✓ | ✓ | ✓ |
| Security, mobile and AI | ||||
| iOS and Android appsListed on the Free plan card; each paid plan includes the plan below it | ✓ | ✓ | ✓ | ✓ |
| Single sign-on (SSO)From the Enterprise plan card | – | – | ✓ | ✓ |
| Two-factor authenticationFrom the Enterprise plan card | – | – | ✓ | ✓ |
| Custom domain | – | – | ✓ | ✓ |
| Zia Insights | – | ✓ | ✓ | ✓ |
| Zoho MCP server for AI models | ✓ | ✓ | ✓ | ✓ |
Zoho Projects plans as listed on Zoho's own pages, checked 24 November 2026: zoho.com/projects/pricing-comparison.html and zoho.com/projects/pricing.html. Values from Zoho's global plan comparison page plus the plan cards on the pricing page; zoho.com has no /en-in/ Projects pricing or comparison page (404 on 2026-11-24). Free plan is for up to 5 users per Zoho's pricing page. Zoho can change what each plan includes, so we check again before your scope.
| Feature | Free | Standard | Professional | Premium | Elite | Ultimate |
|---|---|---|---|---|---|---|
| Users and plan limits | ||||||
| Users includedMore users via the user add-on (not on Free) | 1 + 1 accountant | 3 | 5 | 10 | 15 | 25 |
| Business locations included | – | – | 2 | 3 | 8 | 8 |
| Payroll employees included | – | – | – | 10 | 20 | 20 |
| Invoices per year | 1,000 | 5,000 | 10,000 | 25,000 | 1,00,000 | 1,00,000 |
| Bills and expenses per yearCombined limit | 1,000 | 5,000 | 10,000 | 25,000 | 1,00,000 | 1,00,000 |
| Receipt autoscans per month | 50 | 200 | 200 | 1,000 | 1,000 | 1,000 |
| GST and invoicing | ||||||
| E-way bills | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| GST e-invoicing | – | ✓ | ✓ | ✓ | ✓ | ✓ |
| GST returns, filing and payments | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Invoice Management System (IMS) | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Progress invoicing | – | ✓ | ✓ | ✓ | ✓ | ✓ |
| Retainer invoicing | – | – | ✓ | ✓ | ✓ | ✓ |
| Multi-currency invoicing | – | – | ✓ | ✓ | ✓ | ✓ |
| Customer self-service portal | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Orders, purchases and banking | ||||||
| Sales orders and purchase orders | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Recurring bills | – | – | ✓ | ✓ | ✓ | ✓ |
| Vendor self-service portal | – | – | – | ✓ | ✓ | ✓ |
| Bank reconciliation | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Connected banking with partner banks | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Controls and approvals | ||||||
| Activity log (audit trail) | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Transaction locking | – | ✓ | ✓ | ✓ | ✓ | ✓ |
| Custom user roles and access | – | – | ✓ | ✓ | ✓ | ✓ |
| Sales and purchase approvals | – | – | ✓ | ✓ | ✓ | ✓ |
| Custom approval workflows | – | – | – | 25 | 70 | 70 |
| Budgeting | – | – | – | ✓ | ✓ | ✓ |
| Fixed asset management | – | – | – | ✓ | ✓ | ✓ |
| Projects and inventory | ||||||
| Projects, tasks and timesheet billing | – | – | ✓ | ✓ | ✓ | ✓ |
| Project profitability | – | – | ✓ | ✓ | ✓ | ✓ |
| Stock tracking and reorder points | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Price lists | – | – | ✓ | ✓ | ✓ | ✓ |
| Warehouse management | – | – | – | – | ✓ | ✓ |
| Serial number and batch tracking | – | – | – | – | ✓ | ✓ |
| Bin location tracking | – | – | – | – | 2,000 bins per location | 5,000 bins per location |
| Reports, automation and analytics | ||||||
| Custom reports | – | 10 | 25 | 50 | Unlimited | Unlimited |
| Report builder | – | – | – | ✓ | ✓ | ✓ |
| Cash flow forecasting report | – | – | – | ✓ | ✓ | ✓ |
| Workflow rules | – | – | 10 | 200 | 200 | 200 |
| Blueprints (guided process flows) | – | – | – | – | ✓ | ✓ |
| Advanced analytics and KPI dashboardsPowered by Zoho Analytics, 3 million rows | – | – | – | – | – | ✓ |
| Integrations and support | ||||||
| Zoho CRM, Inventory and Payroll integration | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Zoho People and Projects integration | – | – | ✓ | ✓ | ✓ | ✓ |
| Email support | ✓ | ✓ | ✓ | ✓ | ✓ | ✓ |
| Voice support | – | – | ✓ | ✓ | ✓ | ✓ |
| Chat support | – | – | – | ✓ | ✓ | ✓ |
Zoho Books plans as listed on Zoho's own pages, checked 24 November 2026: zoho.com/in/books/pricing and zoho.com/in/books/pricing/pricing-comparison.html. Free plan: Zoho says it stays free while annual revenue is within 25 lakhs; add-ons are not supported on Free except document autoscans. Business locations: each location add-on includes 1 GSTIN and 10K invoices (Zoho add-on note). Zoho can change what each plan includes, so we check again before your scope.
Ways we build it
Which of our three solar options fits your costing process?
We have delivered many solar projects, and after we see your current cost sheet and project volume, we recommend the option that fits your business from the three below.
Option 1
Zoho Solar
Item rates, kits, CRM quotes and project-tagged costs set up on standard Zoho apps, with an estimate against actual dashboard. Suits firms that mainly need one source of rates and visible project margin.
Option 2
Zoho Solar + Custom costing app
The same base plus a Zoho Creator costing app with your overhead, contingency and margin rules, approval steps for discounts and a link to your design tool's exports.
Option 3
Our complete end-to-end solar product, costing built in
Our complete solar business product, where costing is one stage in a single system that also runs survey, procurement, installation, billing and service.
What clients say
What do our clients say about working with us on Zoho?
These quotes come from our clients in other industries and are already published on our website. The figures on this page are samples, not results from any client.
The team at Elite Tech Corporation is highly knowledgeable and extremely supportive. They took the time to understand each of our business use cases in detail and approached every requirement with a strong implementation mindset.
What stood out most was their structured approach, clarity in communication, and commitment to aligning technology with practical, on-ground operations rather than offering generic solutions.
Your understanding of our requirements and customization of Zoho Books have positively impacted our operations. The successful implementation of APIs and workflows has streamlined processes.
Who wrote this costing guide, and what should you verify yourself?
This guide is written by people who set up quoting, purchase and project accounting systems for solar firms, so it looks at costing from the estimator's desk. We are a Zoho Advanced Partner that builds business software, not a tax adviser, a scheme agency or an approval authority, so treat the sample figures here as arithmetic only.
Rules change; check the official portal before you rely on any scheme, module or tax rule:
- GST rates, registration and returns: gst.gov.in
- Approved module and cell lists, scheme orders: the Ministry of New and Renewable Energy, mnre.gov.in
- Residential rooftop scheme and vendor rules: pmsuryaghar.gov.in
- Net metering and connection steps: your state electricity regulator and DISCOM
Starting out rather than scaling? Our guide on how to start a solar EPC business in India covers registrations, supply and working capital.
FAQ
Questions estimators ask about solar EPC project costing
Bring one recent quote and its actual cost to the meeting, and we will show where the two drifted apart.
Book your meeting with our solar expert todayHow do solar EPC companies calculate project cost?
They price the bill of materials from the design at current supplier rates, add installation labour, transport, lifting, approvals and testing to reach direct cost, then add a share of company overheads and a contingency for the site. The selling price is set from a target margin on that full cost, and the price per watt is checked last.
What is the formula for a solar EPC selling price?
Selling price before tax equals full cost divided by one minus the target margin. For a 12 percent margin you divide full cost by 0.88. Adding 12 percent on top of cost is markup, which leaves a margin of only about 10.7 percent of the price.
Which costs do solar estimators most often forget?
Repeat inspection visits, idle crew days, crane or scaffolding hire, cable route changes after survey, roof waterproofing at anchors, spare modules, monitoring hardware and the free service visits promised in the proposal. Overheads and contingency are also often dropped when a deal is negotiated.
Should GST be included in the solar project cost sheet?
Build cost and price before tax and show GST as a separate line on the quote. Tax you can claim back as input credit is not a project cost. The GST treatment of a solar contract depends on how supply and installation are split, so confirm it with your tax adviser and check gst.gov.in.
Does the rooftop solar subsidy reduce the EPC's project cost?
No. A scheme subsidy is a benefit to the consumer under that scheme's rules and does not change what the plant costs the EPC firm to build. Show the price, the expected subsidy and the customer's payable amount separately. Rules change; check the official portal at pmsuryaghar.gov.in before quoting.
Why is cost per watt higher on small solar systems?
Because survey, design, paperwork, transport and the commissioning visit cost nearly the same for a small system as for a larger one. Spread over fewer watts, these fixed costs raise the figure per watt. Modules and structure scale with size, so their share per watt stays steadier.
How much contingency should a solar EPC estimate carry?
There is no fixed figure. Base it on the site risk: higher for old or uncertain roofs, remote sites and tight shutdown windows, lower for repeat designs on known roofs. Track how much contingency each finished project actually used and set future rates from that record.
Can Zoho calculate solar project cost and track actual cost?
Yes, with setup. Zoho Inventory and Zoho Books hold item rates and project-tagged purchases and expenses, Zoho CRM holds quotes, and Zoho Analytics compares estimate with actual. A costing engine with your overhead, contingency and margin rules is a custom Zoho Creator app. Once we have seen your cost sheet, we recommend the option that fits your business.