Asset owners, O&M contractors and EPC teams · India
Solar performance ratio monitoring, with a reason behind every low month
Solar performance ratio monitoring compares the energy a plant delivered with the energy the measured sunlight should have produced, so you can tell a dusty week from a failing inverter. The PR number itself is worked out in your SCADA or monitoring portal, because it needs irradiance sensors. We connect that number to Zoho, where a drop becomes a task, the cause gets logged and the owner's monthly report writes itself. We have delivered many solar projects, and we say plainly which parts are Zoho and which are custom.
Plant B monthly PR 76.4% vs 79% expectedFrom SCADA · Sample
Soiling check opened on blocks 3 and 4Zoho FSM · Sample
One plant, one reading, one decision
Irradiation on the module plane165 kWh/m²From the POA sensor
Energy at the export meter1,26,000 kWh1,000 kWp plant
Performance ratio76.4%Expected 79%
Loss events logged5Each with a cause
Sample month. The figures are made up to show how the numbers relate.
300+
Zoho projects delivered, solar and beyond
2021
Founded, and building on Zoho since
6 languages
Training in English, Hindi, Marathi, Tamil, Kannada and Malayalam
ZohoAdvancedPartner
Also Zoho Creator Registered, Zoho Catalyst, AWS and Shopify Partner
The number, in plain words
What is the performance ratio of a solar plant?
Performance ratio is the share of the sunlight's potential that a plant actually turned into delivered energy. It divides the plant's final yield (kWh delivered per kWp installed) by its reference yield (the sunlight on the module plane, in kWh per m², divided by 1 kW per m²). Because both sides are scaled to the plant and the weather, PR lets you compare a cloudy month with a sunny one.
PR is not efficiency. A plant can read 78% in July and 74% in April without anything breaking, because hot modules produce less. That is why many owners also track a temperature-corrected PR, and why the expected PR in your design report or O&M contract matters more than any general figure.
The formula most monitoring systems use
PR=EAC ÷ PSTCHPOA ÷ GSTC
EAC
Energy delivered at the export or plant meter in the period, kWh
PSTC
Installed DC capacity at standard test conditions, kWp
HPOA
Irradiation measured on the plane of the modules, kWh/m²
GSTC
Reference irradiance of 1 kW/m²
Which meter, which sensor and which hours count are set in your contract. We copy those rules into the setup; we never pick them for you.
Why you watch PR
Who needs PR monitoring tied to their business system?
Anyone whose money moves when PR moves. An owner wants to know the plant earns what it was bought to earn; a contractor has a PR figure written into its O&M agreement; an EPC may have to prove PR before handover. Pick the position closest to yours.
The plants were bought on a yield estimate; PR shows whether it holds
Your finance team sees revenue, your engineers see inverter screens, and nobody sees both on the same page. The useful setup keeps one record per plant with its expected PR by month, imports the actual figure from each monitoring source, and lists the loss events that explain the gap. Board packs and lender reports then come from one place.
Start withPlant register in a Creator app, monthly PR import, a plant-by-plant gap report
WatchPlants on different monitoring platforms report PR differently; agree one definition first
A PR shortfall can turn into a deduction from your fee
Many O&M agreements carry a committed PR or availability figure and a formula for what happens below it. The dispute is rarely about the number; it is about which hours were the grid's fault, which were the owner's and which were yours. Every outage and curtailment logged with its cause, as it happens, is what protects the fee at month end.
Start withLoss-event log with agreed causes, Zoho Desk tickets for every PR drop, monthly contract statement
WatchGrid-side outages need proof the same day: DISCOM messages, meter logs, photos
The PR test decides when the project is really finished
Some contracts ask the EPC to show a set PR over a test window after commissioning, with calibrated sensors and agreed exclusions. Test plans, sensor calibration certificates, daily readings and the owner's sign-off are scattered across email. Keeping them as one checklist on the project record makes the handover, and any retest, much easier to defend.
Start withTest checklist in Zoho Projects or Creator, sensor certificates in WorkDrive, daily PR import during the window
WatchThe test method is the contract's; the software only records that it was followed
Every lost unit is lost income on a long contract
When you own the plant on a customer's roof and bill per unit, a slow PR slide over two years costs more than one dramatic fault. Seeing PR by roof next to the invoice for that roof shows which sites are drifting and whether a cleaning or a repair would pay for itself before the next billing cycle.
Start withPR per roof beside Zoho Books invoices, drift alert after three low months
WatchSmall roofs rarely have a POA sensor; satellite irradiance needs its own caveat
If you sell power per unit from roofs you own, our RESCO software page covers metering and billing for that model.
How a PR figure travels
What happens between the sunlight sensor and the owner's monthly report?
Six steps. The first three happen at the plant and in your monitoring system; the last three happen in Zoho. Scroll through one sample month for a 1 MWp rooftop plant.
Sunlight measured
Energy metered
PR worked out
PR reaches Zoho
Drop investigated
Owner report
Stage 1
A sensor on the module plane counts the sunlight
A pyranometer or reference cell, tilted like the modules, reads irradiance every few seconds; module temperature sensors sit on the back sheet. Without these, PR is a guess. Small roofs that have no sensor use satellite irradiance instead, which is fine for spotting trends but weaker in a contract dispute.
Sensors and data logger (stay at the plant)
Calibration certificates (Zoho WorkDrive)
Stage 2
Inverters and the export meter count the energy
Inverters report what each one produced; the export or plant meter reports what left the site. Contracts usually name the meter that counts, often the one the DISCOM reads. Where inverter totals and the meter disagree for weeks, that gap is itself a fault to chase: cable losses, a transformer issue or a meter error.
Inverter and meter data (monitoring system)
Meter reading photos on the FSM job (Zoho FSM)
Stage 3
The monitoring system works out daily and monthly PR
SCADA or the monitoring platform divides final yield by reference yield, applies the contract's exclusions where it can and plots the trend. This is specialist software, and it should stay. Zoho does not read sensors, and we do not pretend it does.
SCADA or monitoring platform (stays outside)
Agreed PR definition (recorded in Creator)
Stage 4
Each morning the PR figure lands on the plant record
A scheduled import pulls yesterday's PR, energy and irradiation into the plant's record in a Zoho Creator app, where the platform offers an API or a scheduled export. Each value is stored with its source, so a figure typed in by hand is never mistaken for one the system read.
Zoho Creator plant record (custom)
API or file import (custom, per platform)
Stage 5
A drop below the plant's band opens an investigation
When PR stays under the expected band for the days you set, Zoho Desk opens a ticket on that plant and the engineer checks the usual suspects: soiling, a string down, an inverter derating, a shading change or a faulty sensor. If a visit is needed, a Zoho FSM job goes out with the checklist for that cause.
Zoho Desk ticket with rule (configured)
Zoho FSM site visit (native)
Loss-event log (custom Creator)
Stage 6
The month closes with numbers and reasons on one page
Zoho Analytics joins the imported PR with the tickets, visits and loss events, so the owner sees actual against expected PR, the hours lost by cause and what was done about each one. For a contractor, the same data feeds the monthly contract statement and any invoice adjustment in Zoho Books.
Zoho Analytics report (configured)
Zoho Books invoice (native)
Free PR calculator
How do you calculate one month's performance ratio?
Enter the plant's DC capacity, the month's irradiation on the module plane and the energy at the export meter. The calculator gives reference yield, final yield and PR, and shows how many units the plant fell short of the PR you expect.
Irradiation comes from your POA sensor or the monitoring platform's monthly summary
This is the basic PR; temperature correction and contract exclusions are not applied
Send the result and we will show how the same numbers would sit in Zoho
Reference yield165.0hours at 1 kW/m²
Final yield126.0kWh per kWp
Performance ratio76.4%2.6 points below expected
Units short of expected4,350kWh this month
Estimate only. The default inputs are Sample values, and your figures stay in this browser until you choose to send them.
Where PR lives today
Is a monitoring portal enough for PR, or do you need Zoho as well?
For seeing PR, the portal or SCADA is enough. For acting on it, usually not: a chart does not assign a cleaning crew, record why the grid was down or adjust an invoice. Zoho adds the work and the money around the number. Here is how each handles the same seven jobs:
Four ways to handle solar performance ratio, compared by task
Task
Monthly spreadsheetFigures copied by hand
Inverter maker's portalOne brand per login
SCADA or monitoring platformPlant-level, multi-brand
Monitoring system plus ZohoCreator, Desk, FSM, AnalyticsOur usual suggestion
Calculate PR from sensors
Only from typed totals
Often estimated, sensor optional
Its core job
Monitoring system keeps doing it
One view across brands and plants
If someone keeps it current
One brand only
Yes, for connected plants
Every plant, every source, one register
Expected PR by month per plant
Another sheet
Rarely
Sometimes
Stored on the plant record
A drop becomes an assigned task
No
Email alert
Alarm in the platform
Zoho Desk ticket and FSM visit
Cause logged for each lost hour
Comments column
No
Partly, by event code
Loss log with your agreed causes
Cleaning dates beside the PR trend
No
No
Rarely
FSM jobs on the same chart
Contract statement and invoice adjustment
Calculated in a sheet
No
No
Analytics statement, Books invoice
Already running O&M tickets and PM visits? Our solar O&M software page is the business-level view; this page goes deep on the PR number only.
Technical boundary
Can Zoho calculate the performance ratio by itself?
No. Zoho has no sensor connection and no native PR calculation for solar plants. It can store PR, compare it with targets, raise work and report on it once the figures arrive. Getting them there is a custom integration, and the calculation stays in your monitoring system.
NativeZoho apps, set up for PR work
Tickets, assignment rules and escalation for PR drops in Zoho Desk
Cleaning, IV-curve tracing and sensor checks as visits in Zoho FSM
Reports and dashboards over imported data in Zoho Analytics
Contract invoices and credit notes in Zoho Books
Sensor certificates and test reports in Zoho WorkDrive
Custom buildOn Creator, Catalyst or Flow
Plant register with capacity, expected PR by month and the agreed definition
Daily or monthly import from each monitoring platform's API or export
Drop rules: how many days below which band opens a ticket
Loss-event log with cause, start, end and evidence
Contract statement logic for PR or availability clauses
Stays outsideSpecialist systems
Irradiance and temperature sensors, data loggers
SCADA, plant controller and inverter makers' portals
The PR calculation itself, including temperature correction
Energy yield simulation and design reports
DISCOM meter data and any official reading
By plant type
Does PR monitoring work the same on a home roof and a ground-mount plant?
No. The bigger the plant, the better the sensors and the stricter the contract, so the setup moves from a simple trend alert on small roofs to an hour-by-hour loss log on large plants. Choose your plant type.
Thousands of small systems, no sensor on any of them
A 3 kW home system has an inverter app and no pyranometer. True PR is not possible, but specific yield (kWh per kWp) compared across neighbouring roofs works well: if one roof in a locality yields far less than the others in the same week, something is wrong there. That comparison is a light custom job on Creator.
Inverter app data
Yield per kWp
Compare by locality
Service call
Usually fitsCreator yield table, Desk tickets for outliers
Key setupLocality and tilt on each system record
Watch forCalling a figure PR when no sensor exists
Factory roofs where dust and shading change with the season
Commercial and industrial roofs from 100 kWp upwards often have one sensor and a multi-brand logger. Neighbouring chimneys, cement dust or a new building can pull PR down slowly. Plotting cleaning dates against the PR trend shows the right cleaning interval for each roof.
Logger data
Daily PR
Cleaning dates
Interval review
Usually fitsCreator import, FSM cleaning jobs, Analytics trend
Key setupRoof block on every cleaning job
Watch forFactory shutdown days distorting the month
Large plants with SCADA, several sensors and a strict contract
Ground-mount plants usually run SCADA with sensor redundancy, and the O&M agreement often has PR or availability clauses. Here the value of Zoho is the loss log: every grid outage, curtailment instruction and equipment fault, with start and end times, so the month's PR can be explained hour by hour.
SCADA PR
Loss events
Exclusions agreed
Contract statement
Usually fitsCreator loss log, Desk, FSM, Analytics, Books
Key setupCause list agreed with the owner before go-live
Watch forTwo sensors disagreeing; record which one counted
Power sold to a consumer through the grid
Open-access and captive plants are paid on energy the grid accepts, so meter data and grid availability carry more weight than at a rooftop. PR monitoring here sits beside the energy accounting: banked units, scheduled against actual, and the buyer's monthly statement.
Plant meter
PR and availability
Grid events
Buyer statement
Usually fitsCreator import and energy ledger, Analytics, Books
Key setupGrid-event cause codes separate from plant faults
Watch forState rules on banking change; confirm with your consultant
Rear-side gain and moving rows make the reference harder
Bifacial modules collect light on the back, and trackers change the plane of the modules through the day. The PR definition has to say which irradiance counts, often front-side POA plus a rear sensor. Tracker faults, where a row sticks in one position, show up as a PR dip and deserve their own cause code.
Front and rear sensors
Agreed definition
Tracker events
Report
Usually fitsCreator register with definition notes, Desk, FSM
Key setupTracker row as an asset with its own tickets
Watch forComparing bifacial PR with monofacial plants directly
Reading a low PR
Why does a solar plant's performance ratio drop?
Usually for one of six reasons, and each needs a different response from a different person. Tap a card to see how the cause is spotted and what Zoho records for it.
New shading from a growing tree or a new building is a seventh cause worth its own code: it shows as a dip at the same hours every day.
Three solar options
Which of our solar options fits PR monitoring?
PR monitoring almost always needs some custom work, because the data arrives from outside Zoho. We recommend the option that fits your business once we have seen your plants and your monitoring sources.
Option 1
Zoho Solar, for PR tracking
Zoho apps set up for your solar work, nothing custom. For PR, this suits a small fleet where an engineer enters the monthly PR by hand: Desk tickets for low months, FSM cleaning jobs and an Analytics report. No live import.
Option 2
Zoho Solar + Custom, for PR tracking
The same Zoho apps plus custom apps and integrations: a Creator plant register, imports from each monitoring platform, drop rules, the loss-event log and the contract statement. This is where most PR projects land.
Option 3
Our end-to-end solar product, with PR in it
Our complete solar business product covering the whole value chain, from lead to plant operations, with performance tracking as one part of it. For companies that sell, build and operate plants and want one system for all of it.
License cost
What does PR monitoring on Zoho cost in India?
Licenses go to Zoho at its India prices; our setup is a separate fixed price in your signed scope. A plant register and import on Zoho Creator Professional costs ₹1,200 per user per month, billed yearly, plus GST. Your monitoring platform's own subscription stays as it is.
Zoho Desk Standard for the engineers who handle PR tickets: ₹800 per user per month, billed yearly, plus GST
Zoho Flow Standard for simpler file or email imports: ₹1,450 a month billed yearly for 5,000 tasks a month, plus GST
Monitoring APIs sometimes carry their own fee from the platform; we check that during scoping
Zoho India list prices as recorded in November 2026; Zoho can change them, so we confirm current prices during scoping. We quote Zoho Analytics separately, because its edition depends on how many people read the reports. To see what moves the setup fee, read what drives Zoho implementation cost.
Connections
How does PR data get from SCADA or an inverter portal into Zoho?
Through the platform's API where it has one, through a scheduled file export where it does not, and by hand as the last resort. Every route is custom work that we test on one of your plants before it goes into the scope. Look for the label on every link.
Plant data in
Where the number comes from
Custom Monitoring platform or SCADA API into a Creator plant record
Custom Scheduled CSV or email report parsed by Zoho Flow
Custom Satellite irradiance import for roofs without sensors
Work out
What the team does about it
Native Zoho Desk ticket linked to a Zoho FSM visit
Native Readings, photos and IV-curve files from the FSM app
Native Alerts to the plant's engineer in Zoho Cliq
Reports and money
Who hears about it
Native Analytics reports over Creator, Desk and FSM data
Native Contract invoices and credit notes in Zoho Books
Custom Owner portal showing each plant's PR and events
How do we set up PR monitoring on Zoho for your plants?
Definition first, data second, rules third. If two people in your company calculate PR differently, no software will fix that, so we settle it before building anything. Dates are agreed in the signed scope once we have seen your plant list and monitoring sources.
1Trace one PR figureWe take last month's PR for one plant and follow it back to the sensor, the meter and every event that touched it.
2Fix the definitionWhich meter, which sensor, which hours and which exclusions, written down per plant and per contract.
3Build the registerPlants, capacity, expected PR by month and owners go into the Creator app, checked by your engineers.
4Connect one sourceThe import from one monitoring platform runs in parallel with your spreadsheet until the figures match.
5Switch on the rulesDrop bands, Desk tickets, FSM visit templates and the loss-cause list go live plant by plant.
6Report and trainOwner reports in Analytics, and engineers trained in English, Hindi, Marathi, Tamil, Kannada or Malayalam.
Where we work
Can you set up PR monitoring for plants in different states?
Yes. The data already travels over the internet, so most of the work is remote. We visit a plant or your control room when seeing the sensors and meters in person helps, from our Bengaluru, Kochi and Coimbatore offices.
Vasanth Nagar, Bengaluru
Book a slot at #39, 8th Main Road, Vasanth Nagar, and bring one month's PR export and the O&M agreement clause it is measured against.
Karnataka rooftops
Running rooftops around Bengaluru? Our Bangalore solar software page shows the full rooftop business in a Karnataka setting.
Plants across India
For ground-mount, open-access and C&I plants in other states, one site visit during discovery is usually enough to see the sensors and the meter.
Engineer training
Plant engineers learn the Desk and FSM screens in English, Hindi, Marathi, Tamil, Kannada or Malayalam, with short recordings they can watch again.
Client feedback
Who vouches for the way Elite Tech Corp works?
We have delivered many solar projects, yet the reviews below come from published Elite Tech Corp clients in other industries; every plant figure on this page is a Sample.
The team at Elite Tech Corporation is highly knowledgeable and extremely supportive. They took the time to understand each of our business use cases in detail and approached every requirement with a strong implementation mindset.
KVP EnterprisesFounder and CEO · manufacturing automation
What stood out most was their structured approach, clarity in communication, and commitment to aligning technology with practical, on-ground operations rather than offering generic solutions.
MegawinFounder and CEO · multiple Zoho applications
Your understanding of our requirements and customization of Zoho Books have positively impacted our operations. The successful implementation of APIs and workflows has streamlined processes.
F Care GroupFounder and CEO · Zoho Books, APIs, workflows
FAQ
Solar performance ratio questions
Stuck on a PR question for your own plants? Ask the solar expert who reviews plant setups.
It is the practice of tracking, day by day and month by month, how much of the sunlight's potential a solar plant turns into delivered energy, and acting when that share falls. The PR figure comes from irradiance sensors and meters through SCADA or a monitoring platform; the monitoring part is what you do with it: compare it with the expected figure, find the cause of a drop, fix it and report it.
How is the performance ratio of a solar plant calculated?
Divide the final yield by the reference yield. Final yield is the energy delivered in the period divided by the plant's DC capacity in kWp. Reference yield is the irradiation measured on the module plane in kWh per square metre, divided by the reference irradiance of 1 kW per square metre. For example, a 1,000 kWp plant that delivers 1,26,000 kWh in a month with 165 kWh per square metre of irradiation has a PR of about 76.4% (Sample figures).
Can Zoho calculate the performance ratio of a solar plant?
Not natively. Zoho has no connection to irradiance sensors or inverters, so the calculation stays in your SCADA or monitoring platform. Zoho receives the PR figure through a custom import, compares it with the plant's expected value, opens a ticket when it drops and reports on it alongside the work done.
What is the difference between PR and plant availability?
Availability measures the time the plant was able to generate, whatever the weather. PR measures how well it converted the sunlight it received. A plant can be fully available and still have a low PR because the modules are dirty, and many O&M agreements track both figures with different rules.
Why is PR lower in summer even when nothing is broken?
Solar modules lose output as they heat up, so hot months show a lower basic PR. A temperature-corrected PR adjusts for module temperature and gives a fairer month-to-month view. The report should always say which of the two figures it shows.
Can PR be monitored on home rooftop systems without a sensor?
Not true PR, because there is no measured irradiance. What works is comparing specific yield, the kWh per kWp, across nearby systems in the same week, or using satellite irradiance data. Both are good for spotting a faulty system, but neither should be presented to a customer as a measured PR.
Which monitoring platforms can send PR data to Zoho?
Any platform that offers an API or a scheduled export, such as a daily CSV or email report, can feed Zoho through a custom connector. Support differs by platform and sometimes needs a paid plan from the platform, so we check your exact platforms and test one plant before the work is scoped.
How much does solar PR monitoring on Zoho cost in India?
Zoho licenses are paid at Zoho's India prices, for example Zoho Creator Professional at ₹1,200 per user per month and Zoho Desk Standard at ₹800 per user per month, both billed yearly, plus GST. Our setup, including the import and the loss log, is a fixed price in your signed scope after a free first meeting.
Can a PR shortfall in an O&M contract be worked out in Zoho?
Yes, once the contract's formula and exclusions are agreed and the PR figures and loss events are in Zoho. A custom statement applies the clause each month and Zoho Books raises the invoice or credit note. The formula itself always comes from your signed agreement, never from us.