PPAP 18 elements and submission levels 1 to 5, explained for Indian auto suppliers
A full PPAP (Production Part Approval Process) has 18 elements, from design records and the process FMEA to sample parts and the Part Submission Warrant. The submission level, 1 to 5, decides how much of that evidence you send to the customer and how much you keep at your plant ready for review. Level 3 is the default when the buyer names nothing else. Every level needs the warrant, and every level still expects you to hold all the applicable records.
We reply within 1 business hour · No obligation · Check your pack in two minutes
Also Zoho Creator Registered, Zoho Catalyst, AWS and Shopify Partner
Most suppliers meet PPAP when a buyer's supplier quality engineer sends a part number, a drawing revision and a due date for the "PPAP pack", with no word on what the 18 elements are or why the level matters. This guide covers both, so quality, engineering and production agree on one checklist before work starts.
PPAP comes from the Automotive Industry Action Group (AIAG) and its fourth edition is still the reference most buyers quote. IATF 16949 asks certified suppliers to run a product approval process the customer recognises (clause 8.3.4.4), so PPAP or an equivalent such as the German VDA PPA shows up across Indian supply chains, whether you ship to a Pune vehicle plant or an exporter in Chennai. Buyers often add their own forms on top.
One thing to settle early: the level changes what you post, upload or carry to the buyer. It never changes what you must have ready. A Level 1 supplier still keeps the control plan, the FMEA and the capability study on file.
The evidence set
What are the 18 PPAP elements?
The 18 elements fall into five jobs: show the design you were given, show how you planned the process, prove your measurements and results, hand over physical parts, and sign the warrant. Read them in that order and the list stops looking like paperwork.
The design you were given
- Design recordsThe released drawing and specifications for the part, including any material callouts. If the customer owns the design, you hold their copy at the correct revision.
- Engineering change documentsSigned records of any change not yet shown on the drawing, so the revision you build matches the revision the buyer approved.
- Customer engineering approvalProof that the buyer's engineering team has cleared items such as a trial run or a deviation, where their manual asks for it.
- Design FMEANeeded only when you are design responsible. It lists how the design could fail, how severe that would be and what prevents it.
How you planned the process
- Process flow diagramEvery operation from receiving raw material to packing, including rework loops and inspection points.
- Process FMEAThe same risk thinking as the design FMEA, applied to each step on the flow diagram, with actions for the high risks.
- Control planWhat you check at each step, how often, with which gauge and what the operator does when a result goes out of limits.
Proof from measurement and testing
- MSA studiesGauge repeatability and reproducibility and related studies showing your measuring equipment can be trusted for the features it checks.
- Dimensional resultsEvery dimension and note on the drawing, measured on the sample parts and marked as within or outside tolerance. Ballooned drawings make this easier to audit.
- Material and performance test recordsChemistry, hardness, plating, salt spray or functional test results the drawing or specification demands.
- Initial process studiesCapability or performance indices (Cpk, Ppk) for the special characteristics, taken from a real production run.
- Qualified laboratory documentationThe scope and accreditation of each lab that produced your results, whether in-house or outside, for example NABL accreditation in India.
Physical parts and aids
- Appearance approval reportOnly for parts with colour, grain or surface finish requirements that the buyer judges by eye.
- Sample production partsParts from the significant production run, in the quantity the buyer asks for.
- Master sampleOne part you keep, approved and labelled, as the physical reference for later disputes and operator training.
- Checking aidsFixtures, templates and gauges built for this part, with their calibration and design records.
The buyer's rules and your signature
- Customer-specific requirementsRecords showing you met each extra rule in the buyer's supplier manual, from packaging trials to their own forms.
- Part Submission Warrant (PSW)The one-page summary that declares the part meets every requirement, with part weight, reason for submission and level, signed by an authorised person.
Elements that do not apply, such as the design FMEA for a build-to-print supplier, get "not applicable" and a reason, never a blank.
Submission levels
What do PPAP submission levels 1 to 5 mean?
The level sets what leaves your plant. Level 1 sends only the warrant, Level 3 sends the warrant with samples and the complete data, and Level 5 keeps the full pack at your site for the buyer to review in person. Pick a level below to see what moves and what stays.
Level 1: the warrant alone
You send the signed PSW, plus the appearance approval report when the part has a visible finish requirement. Buyers tend to use it for low-risk items such as standard hardware, bulk material or a repeat order of a part already approved.
- Travels to the buyerPSW (and appearance report where it applies)
- Stays with youAll other applicable elements
- Watch forTreating Level 1 as permission to skip the control plan
Level 2: warrant, samples and limited data
You send the PSW, sample parts and a selected part of the evidence, typically design records, dimensional results and material test reports. The buyer names the selection, so read the request line by line.
- Travels to the buyerPSW, samples, the data they list
- Stays with youFMEAs, control plan, MSA, capability studies
- Watch forAssuming the same subset as the last buyer
Level 3: warrant, samples and complete data
This is the level that applies when the buyer does not name another one. You send the PSW, sample parts and the full supporting set for every applicable element. Physical items such as the master sample and checking aids normally stay at your plant, available on request.
- Travels to the buyerPSW, samples and all applicable records
- Stays with youMaster sample, checking aids
- Watch forCapability data from trial parts instead of a real run
Level 4: warrant plus what the buyer defines
The buyer writes its own list. It may be close to Level 3, or it may add items such as a packaging trial, a run-at-rate report or the buyer's own templates. Level 4 is common where an OEM has a strong supplier manual of its own.
- Travels to the buyerPSW and whatever the buyer specifies
- Stays with youEverything else that applies
- Watch forVerbal changes to the list that nobody records
Level 5: full review at your plant
You send the PSW and samples, and the buyer reviews the complete data at your manufacturing site, often while walking the line. It is used for critical parts, new suppliers or a launch after quality problems.
- Travels to the buyerPSW and samples
- Stays with youThe full pack, reviewed on site
- Watch forRecords that exist but take an hour to find during the visit
Who picks the level? The customer, on the request or the purchase order; with nothing written, Level 3 applies. Raise a Level 4 or 5 demand at quotation, since the extra engineering hours belong in the price. The AIAG manual marks each element as submit or retain per level, and the buyer's manual can change that table.
Resubmission
When does a supplier have to submit PPAP again?
Any change that could affect form, fit or function needs the buyer told first and usually a fresh submission. The common triggers are listed here; your buyer's manual may add more or waive some.
- A new part or a new revisionA part number never supplied before, or a drawing change on an approved one.
- Tooling changesNew, replaced or refurbished tools and dies, or tooling moved to another plant.
- Process or material changesA different manufacturing method, heat treatment route, raw material grade or material source.
- A new sub-supplierPlating, forging, casting or heat treatment moved to a vendor the buyer has not approved for this part.
- Idle toolingProduction restarting after tooling sat unused for twelve months or more, per the AIAG manual.
- Correcting a discrepancyFixing a nonconformance found on an earlier submission or in the field.
The significant production run behind a submission is normally one to eight hours with at least 300 consecutive parts, unless the buyer says otherwise, on real tooling and at real speed.
Common returns
Why do PPAP packs come back rejected?
Most rejections are consistency problems, not engineering ones: the drawing revision, the flow diagram, the FMEA and the control plan disagree with each other. Flip each card for the correction that usually clears it.
What goes on the Part Submission Warrant, and what can the buyer decide?
The PSW names the part, drawing revision, the plant that makes it, the reason for submission, the requested level and the part weight. It declares that the samples represent production and that every requirement is met, under an authorised signature from your organisation.
The buyer then returns one of three decisions:
- Approved: you may ship production quantities against the agreed schedule.
- Interim approval: shipments may go for a limited time or quantity while you close the stated gaps, usually with an action plan and a resubmission date.
- Rejected: no production shipments until a corrected pack is approved.
Interim approval is where tracking slips: keep its open actions, expiry date and quantity limit on the part record, or shipping can carry on after the window closes.
Running PPAP on Zoho
How can a supplier track the 18 elements on Zoho?
Zoho has no ready-made PPAP module. The practical route is a PPAP tracker built in Zoho Creator, store each part's files in Zoho WorkDrive and link the request to the customer account in Zoho CRM. Measuring and statistics tools stay where they are.
- 1Request loggedThe buyer's part number, revision, level and due date become one record on the customer account.
- 2Elements generatedThe 18 elements appear as tasks, with not-applicable reasons and the buyer's extra items added.
- 3Owners assignedDesign, process, metrology and lab tasks go to named roles with due dates before the run.
- 4Files attachedReports land in the part's WorkDrive folder, tagged by element and revision.
- 5Quality reviewThe quality head checks revision and operation numbers line up, then signs off the warrant.
- 6Disposition keptApproved, interim or rejected is recorded, with interim expiry dates sending reminders.
Which PPAP tools keep their job
CMM software, SPC packages, MSA calculations, CAD and your FMEA tool keep doing that work. Zoho holds the exported reports, each element's status and the approval history, and connects to a dedicated quality system rather than replacing it.
What it costs in licenses
Zoho Creator is ₹480 per user per month on the Standard edition and ₹1,200 on Professional, both billed yearly, plus GST, from Zoho's India prices. Only the people who edit records need a license. We set the tracker up for one price, written into the scope you sign before work begins. The Zoho Creator product page lists what the platform includes.
For the full commercial picture, see our PPAP workflow software on Zoho. If your buyer also runs APQP gates before PPAP, the APQP phase gate setup on Zoho carries the same part record from quote to launch.
Free pack check
Is your next PPAP pack ready to submit?
Tick what is already closed for your next part. Copy the result into your internal review, or send it to us and we will suggest how to track the open items.
What should suppliers around Pune, Chakan and Aurangabad plan for?
Western India's auto belt runs from Pimpri-Chinchwad and Chakan to Ranjangaon and Aurangabad, where Tier 2 and Tier 3 machining, forging, plastics and harness units often answer several buyers at once, each with its own supplier manual, level habits and upload portal. The hard part is not knowing the 18 elements; it is keeping four buyers' versions of them apart.
That is where one part record per customer, with the buyer's level and extra items attached, saves the most time. Our Bangalore team works with Pune, Chakan and Aurangabad companies on video calls and on-site visits when needed, and trains plant teams in Marathi and Hindi as well as English. Read our page on Zoho for automotive suppliers in Pune, or see how plant teams there use Zoho Creator apps on the shop floor.
For the standards behind PPAP, our IATF 16949, PPAP and APQP guide covers how the three fit together. Once parts are approved, lot traceability for warranty claims is the next record buyers ask about. Aerospace suppliers face a close cousin of PPAP, explained in our note on AS9100 first article inspection.
A note on compliance: software keeps evidence in order; it does not approve parts. Your quality head and your customer decide whether a pack meets IATF 16949 and the buyer's rules. Our wider Zoho setup for automotive and auto parts makers follows the same line.
FAQ
PPAP elements and levels: common questions
Working on a pack right now? Send us the part and the level, and we will show you how to track it.
Book my free Zoho fit assessmentWhat are the 18 elements of PPAP?
Design records, engineering change documents, customer engineering approval, design FMEA, process flow diagram, process FMEA, control plan, measurement system analysis studies, dimensional results, material and performance test records, initial process studies, qualified laboratory documentation, appearance approval report, sample production parts, master sample, checking aids, customer-specific requirement records and the Part Submission Warrant.
Which PPAP level is the default?
Level 3. When the buyer does not name a level, you submit the warrant, sample parts and the complete supporting data for every applicable element, while physical items such as the master sample and checking aids stay at your plant.
What is the difference between PPAP Level 3 and Level 5?
Both cover the full evidence set. At Level 3 you send the complete data to the buyer. At Level 5 the buyer reviews that complete data at your manufacturing site, usually while also looking at the line that makes the part.
Does a Level 1 PPAP mean we only need the warrant?
Only the warrant (and the appearance report where it applies) is sent. You must still hold every other applicable element, such as the control plan, FMEAs and capability studies, ready for the buyer to ask for.
Is the design FMEA needed if we only make parts to the customer's drawing?
Usually not. The design FMEA belongs to whoever is design responsible. A build-to-print supplier normally marks it not applicable with a short reason, but the process FMEA is always needed.
How many parts go into the PPAP production run?
The AIAG manual describes a significant production run of one to eight hours with at least 300 consecutive parts, made on production tooling at production rate. Your buyer may set a different quantity, so follow their request.
Can Zoho approve or certify a PPAP?
No. Zoho stores and tracks the evidence, tasks and decisions. The approval comes from your customer, and your quality head signs the warrant. We set up Zoho Creator, WorkDrive and CRM so the records stay linked and easy to produce during an audit.